Client: ReWa
Status: Ongoing
Cost: $630,000

General Description

Renewable Water Resources (ReWa) owns and operated an existing pump station that was in need of replacement. This project included a new 200 gpm duplex suction-lift station in a fiberglass enclosure, new 1,000 ft 4-inch force main, electrical / controls, and site improvements.

Innovative Concepts

Unique project features included elevated pump station and electrical platforms to meet county flood proofing requirements, force main installation through a wetland, and connection to a 54” gravity sewer line.